Using the root definition/goal, conceptual model and gap analysis, it is possible to define objectives for the project. Objectives are:
For each objective we need to list the performance indicators - that will measure the achievement or non-achievement of an objective.
The objectives state what it is that we would like to achieve while the performance indicators state how we would measure our performance.
Objective | Performance indicator |
---|---|
Reduction in noise induced hearing loss by 100% within 5 years | Annual no. of workers screened for hearing loss. Average % of workers using PPE per week |
Reduction in STIs treated by 50% within 6 months | % of workers treated for STIs per month No. of condoms issued per month No. of education training sessions conducted per year |
Re-engineering of plant to reduce air pollution by 95% within 5 years | Emissions measured - expressed per month No. of complaints received from neighbours per month. |
From your conceptual model above, identify three objectives and develop three performance indicators that you would use to monitor the outcome of the project.